We are so glad that Grapevine Citizens voted yes for the 2017 Capital Bond Program. Construction is well on its way and here is a sneak peek at the renderings of the proposed fire stations. Just as a reminder here are a few quick facts about each fire station. We anticipate construction completion in December of 2020.
Station 2
/ImageRepository/Document?documentID=7074
Fire Station 2 is located at 3091 Dove Road. It will have four apparatus bays with support spaces totaling some 14,800 square feet. The 1928 Model A Grapevine Fire Engine will be on display in the front foyer.
Station 3
/ImageRepository/Document?documentID=7075
Fire Station 3 is located at 3100 Timberline Drive. It will have three apparatus bays with support spaces totaling some 13,700 square feet. This station will include a Self-Contained Breathing Apparatus Compressor to serve fire stations 3 & 4.